VIEW PROJECT
Lot no:
20162
Project title:
Construction of a block of 2 Classrooms wth Children Restroom and toilet
Location:
Jamila, Kagarko
Contractor:
Alh. Sarki Mailemu Global Links Nig Ltd
Award date:
29/01/18
Completion date:
8 weeks
Contract sum:
9,414,762.00
Revised contract sum:
9,414,762.00
Amount paid:
9,274,433.70
Balance on contract sum:
140,328.30
Unpaid CVs:
NIL
Value of work done:
9,274,433.70
Percentage completion:
100
Remarks:
Year:
2016